754
F. Supp. 1450
BLUE
OCEAN PRESERVATION SOCIETY, a Hawaii non‑profit corporation; Sierra Club,
a
California non‑profit corporation;
and Greenpeace Foundation, a Hawaii non‑
profit
corporation, Plaintiffs,
v.
James
D. WATKINS, Secretary Department of Energy, et al., Defendants.
Civ.
No. 90‑00407 DAE.
United
States District Court,
D.
Hawai'i.
Jan.
8, 1991.
Daniel A. Bent, U.S. Atty., Linda J. Joachim,
Asst. U.S. Atty., Honolulu, Hawaii, and Gary B. Randall, Atty., U.S. Dept.
of Justice, Washington, D.C., for defendants.
ORDER
DENYING DEFENDANT UNITED STATES' MOTION FOR SUMMARY JUDGMENT AND GRANTING
PLAINTIFFS'
MOTION FOR PARTIAL SUMMARY JUDGMENT
DAVID A. EZRA, District Judge.
I. Introduction
This is an action brought by three environmental
groups ("Plaintiffs") seeking to compel the federal government to
prepare an Environmental Impact Statement ("EIS") covering the development
of geothermal energy on the Island of Hawaii (the "Big Island")
before proceeding further with that development. Defendant federal departments
and agencies (collectively the "Government") have moved for summary
judgment on the grounds that Plaintiffs' claim is not ripe, and that this
court therefore lacks subject matter jurisdiction. Plaintiffs have filed a cross‑motion
for partial summary judgment on the issue of whether the geothermal project
constitutes "major federal action" within the meaning of 42 U.S.C.
§ 4332(2)(C). This motion presents
a major question for resolution in this action.
II. Factual Background
A. The 4‑Phase Hawaii Geothermal
Project
In 1978, in order to encourage the commercial
development of geothermal energy, the State of Hawaii, with the cooperation
of Congress and the Department of Energy, began the Hawaii Geothermal Project
(the "Project"). It was envisioned that the *1453 Project would be carried out in four stages: (1) the
Hawaii Geothermal Resource Assessment Program ("Phase I"), (2) the
Hawaii Deep Water Cable Program ("Phase II"), (3) the Hawaii Geothermal
Resource Verification and Characterization Program ("Phase III"),
and (4) Construction of the Commercial Hawaii Geothermal Project ("Phase
IV"). The Project was intended
to provide large quantities of electric power, [FN1] generated by geothermal
energy plants on the side of the Big Island's Kilauea volcano, and transported
to the islands of Maui and Oahu via underwater and overland cable.
The early phases were to be carried out primarily with public funds
to remove the uncertainty and risk, and thereby encourage private investors
to undertake the ultimate Project development (Phase IV).
FN1. The Project clearly contemplates the provision of 500
megawatts of power (enough to meet half the power needs of the State of Hawaii).
It is not clear from the record, however, whether this specific amount
was projected from the beginning, or whether it was determined using the data
gathered in Phase I.
Phase I was jointly funded by
the State of Hawaii and the U.S. Department of Energy ("DOE"), with
the federal government contributing $10.7 million, 80% of the total funding.
It resulted in the drilling of one geothermal well and the establishment
of a small 2.5 megawatt demonstration plant (recently closed down) in the
Puna district on the Big Island. Phase
I provided important data on the geothermal resource base and has now been
completed.
Phase II, the Deep Water Cable
Program, was a study of the feasibility of transmitting electricity via a
submarine cable system from the Big Island to Maui and Oahu. The federal government provided over $24
million (83% of total cost) for the research, design, construction and routing
of an undersea cable. This included not only generic cable development research,
but also site‑ specific route surveys between the islands as well as
actual test‑laying of cable on site. At‑sea tests have been finished and this phase is essentially
completed.
In conjunction with these first
two phases of the Project, the Hawaii legislature has enacted a series of
laws designed to further the Project, which it terms a "federal/state
partnership effort." See
the 1988 Act, discussed infra at Section II.B. These include laws granting favorable excise tax treatment
to sellers of geothermal energy (1978‑Act No. 135), designating geothermal
subzones for development purposes (1983‑Act No. 296), and granting agency
authority to set geothermal royalty rates (1985‑Act No. 138).
Phase III has now begun, with
Congress having already appropriated $5 million of federal funds toward it.
It involves the drilling of 25 commercial scale exploration wells throughout
the Kilauea East Rift Zone to "verify" the geothermal resource. As a preliminary matter in this phase, two slim‑bore
scientific observation holes have, at state (not federal) expense, already
been drilled. Completion of Phase
III will clear the way and set forces in motion for the private construction
of the full‑scale 500 megawatt project, which is Phase IV. [FN2]
FN2. Hawaii Governor John Waihee, in his formal request for
federal funding for Phase III, characterized that phase as follows:
Mr. Chairman, we are not asking for funding for just another
study of renewable energy technology. Our proposal is for a resource verification program which will
lead immediately to a full‑scale private development of 500 megawatts
of geothermal power.
Letter to J. Bennett Johnston, Chairman of Subcommittee on
Energy and Water Development, June 19, 1989, p. 2.
B. The Geothermal and Cable
System Development Permitting Act of 1988
In 1988, to further accelerate
and facilitate the Project, the Hawaii legislature enacted the "Geothermal
and Cable System Development Permitting Act" (the "1988 Act"),
codified at H.R.S. §§ 196D‑1, et seq. The 1988 Act is designed primarily to
streamline the approval and permit process.
The 1988 Act defined the Project
in terms of its ultimate goal (Phase IV), and *1454 specifically recognized the interdependence of its
two fundamental components:
(7) The fundamental interrelationship between the development
of geothermal resources and a cable system and the magnitude of the cost to
undertake each of these developments clearly indicate that neither will be
undertaken without the firm assurance that the other also will be undertaken
in a synchronized and coordinated manner to enable both developments in substance
to be completed concurrently....
H.R.S. § 196D‑2
(emphasis added).
In addition, the 1988
Act established the Interagency Group, a body with representatives from each
agency deemed to have jurisdiction or permitting authority over some aspect
of the Project. Under the statute,
eight state agencies were represented and eight federal agencies (all of whom
are named defendants) were invited to join the group. All eight accepted the invitation, and seven sent representatives
to some or all of the meetings of the Interagency Group. [FN3]
FN3. The federal members of the Interagency Group are the
U.S. Army Corps of Engineers, U.S. Pacific Fleet, U.S. Coast Guard, U.S. Geological
Survey, U.S. Fish and Wildlife Service, National Marine Fisheries Service,
National Park Service, and Environmental Protection Agency ("EPA").
The EPA has been unable to provide a representative because of a staffing
shortage in its Honolulu office. It
has, nonetheless, requested to be kept on board in a non‑attending capacity
and to be kept apprised of matters of interest to the Interagency Group.
The Interagency Group's mission
is to consolidate and streamline the permitting process for the Project.
The purpose is to overcome the daunting array of federal, state and
local permits and processes that have discouraged potential commercial developers. The Group has compiled a master list of
necessary permits, and it is expected that it will be involved in establishing
a timetable for regulatory review, conducting necessary hearings, and consolidating
governmental activities.
C. The Extent of Federal Involvement
in the Project
In addition to the contribution
of federal funds, and the arguably significant role various federal agencies
and officials have played as part of the Interagency Group, the federal government
has been involved in the Project in a number of other ways.
As early as 1978, DOE contracted
with a private consultant for a "Direct Use Overview for Hawaii and Total
Use Scenario for Puna (HI)." [FN4] The purpose of the resulting report is stated in its Summary:
FN4. The report bearing this title was prepared for DOE by
Science Application, Inc., La Jolla, California, under Contract ET‑78‑C‑03‑1529,
on January 12, 1979.
As a means of accelerating the environmentally acceptable
use of geothermal resources in the State of Hawaii, this report presents an
overview of the potential for direct utilization (non‑electric) in the
state and a scenario for development to the year 2020 of the most promising
prospect‑‑Puna, on the Big Island of Hawaii.
This document, commissioned
by DOE, sets forth a series of recommendations for the development of geothermal
energy in the Puna district. It has provided groundwork and guidance for much
of the Project.
DOE has provided planning
and financial assistance in a number of actions aimed at driving commercial
geothermal development forward, independent of its participation in the phases
of the Project itself. Plaintiffs
have submitted a list of 21 DOE‑sponsored reports, funded by DOE contracts,
that deal specifically with geothermal energy development in Hawaii.
In addition, when the state passed legislation for the designation
of resource subzones, DOE provided most of the funding for the necessary geothermal
resource assessment and impact analysis.
More recently, Patricia
Port, Regional Environmental Officer for the U.S. Department of Interior conducted
two meetings in October 1989 and June 1990 with state officers and the National
Park Service, the Fish and Wildlife Service, and the U.S. Geological Survey.
These meetings monitored progress on the Hawaii Geothermal *1455 Project Master Plan, and were designed to share information on agency
concerns so the Master Plan could be adjusted to mitigate such concerns and
facilitate expeditious implementation.
A third such meeting was scheduled for December 1990.
Additionally, it appears
that every federal agency named as a defendant in this action will have some
role in permitting the Project when it reaches Phase IV.
The Government's role
in the Project has not gone unacknowledged. As already noted, in the 1988 Act, the Hawaii legislature described
the Project as a "federal/state partnership." This "partnership" characterization
of the Project has been echoed a number of times in various contexts.
The 1990 Proposal to Congress
for funding for Phase III utilized the heading: "HAWAII GEOTHERMAL PROJECT: A Federal‑State‑Private Partnership
Leading Toward Commercialization." That Proposal explained that "[a] government‑private‑partnership
is ... necessary to prove the resource and allow private commercial development
to go forward."
In May 1990 U.S. Senator
Daniel Inouye sent a letter to one of his colleagues regarding the 1990 Proposal
in which he stated that the total funding of Phase III would "be divided
equally between the private sector and a State and Federal government partnership."
(Emphasis added.)
In January 1990, DOE held
a hearing in Honolulu on "National Energy Strategies." At this meeting, the Director of Hawaii's
Department of Business and Economic Development ("DBED") confirmed
its request to DOE of $15 million (spread over three years in $5 million increments)
for Phase III. The Director stated:
"This is an excellent example of government money, state and federal,
being used in a good way: as
seed money to prepare the way for the private sector to do the project with
reduced risk." At this hearing,
the state made a specific plea for DOE's continued support of and participation
in the Project.
This "continuation"
theme is also reflected in the record. Governor Waihee, in letters to the House
and Senate Appropriation Committees, requested "continuation of the federal
assistance for the Hawaii geothermal research and development project through
the funding of [Phase III]." Similarly,
the 1989 and 1990 Proposals ask that "the Federal government continue
its support of the Hawaii Geothermal Project by joining the State and private
developers in financing [Phase III]."
III. Summary Judgment
Standards
Summary judgment is proper
when there is no genuine issue of material fact and the moving party is entitled
to judgment as a matter of law. Fed.R.Civ.P. 56(c); Retail Clerks Union, Local 648 v. Hub
Pharmacy, Inc., 707 F.2d 1030 (9th Cir.1983).
In ruling on a motion for summary judgment, this court views the facts
and inferences in the light most favorable to the non‑moving party. Id.
The moving party has
the initial burden of "identifying for the court those portions of the
materials on file in the case that it believes demonstrate the absence of
any genuine issue of material fact."
T.W. Elec. Serv., Inc. v. Pacific Elec. Contractors Ass'n, 809 F.2d
626, 630 (9th Cir.1987) (citing Celotex Corp. v. Catrett, 477 U.S. 317, 323,
106 S.Ct. 2548, 2552, 91 L.Ed.2d 265 (1986)).
If the moving party meets its burden, then the opposing party may not
defeat a motion for summary judgment in the absence of any significant probative
evidence tending to support his legal theory. Commodity Futures Trading Comm'n
v. Savage, 611 F.2d 270, 282 (9th Cir.1979). The opposing party cannot stand on its
pleadings, nor can it simply assert that it will be able to discredit the
movant's evidence at trial. See
T.W. Elec., 809 F.2d at 630.
There is no genuine issue
of fact if the opposing party fails to offer evidence sufficient to establish
the existence of an element essential to that party's case. Celotex, 477 U.S. at 322, 106 S.Ct. at
2552. There is also no issue
of fact if on the record as a whole, a rational trier of fact could not find
in favor of the non‑moving *1456
party. Taylor v. List, 880 F.2d
1040, 1045 (9th Cir.1989).
IV. Statutory Background‑‑The
National Environmental Policy Act ("NEPA")
Section 102(2)(C) of NEPA
requires federal agencies to prepare and file an EIS before undertaking "major
federal action significantly affecting the quality of the human environment."
42 U.S.C. § 4332(2)(C). In
Baltimore Gas & Electric v. Natural Resources Defense Council, 462 U.S.
87, 97, 103 S.Ct. 2246, 2252, 76 L.Ed.2d 437 (1982) the U.S. Supreme Court
identified the twin aims of NEPA: (1)
it obligates the agency " 'to consider every significant aspect of the
environmental impact of a proposed action;' and (2) it ensures that the agency
will inform the public that it has considered such environmental concerns
in its decisionmaking process." (quoting Vermont Yankee Nuclear Power
Corp. v. Natural Resources Defense Council, Inc., 435 U.S. 519, 553, 98 S.Ct.
1197, 1216, 55 L.Ed.2d 460 (1978)).
NEPA does not indicate the weight that should be given such environmental
concerns. It requires "only that the agency
take a 'hard look' at the environmental consequences before taking a major
action." Baltimore Gas,
462 U.S. at 97, 103 S.Ct. at 2252.
This case raises issues
concerning what prompts or triggers NEPA obligations, what is the proper scope
of the EIS, and, most importantly at this stage in the proceedings, when an
EIS is required and when can it be compelled by legal action.
V. The Government's Summary
Judgment Motion
The Government has moved
for summary judgment on the grounds that the court lacks subject matter jurisdiction.
Specifically, the Government contends that the suit to compel an EIS
is moot with respect to Phases I and II since those are completed actions,
and that it is unripe with respect to Phases III and IV because no specific
proposal has been advanced for either of them.
A fundamental issue on
the Government's ripeness argument is whether the Project can and/or should
be treated as a single project for NEPA purposes. The Government's ripeness
arguments presuppose that the Project is nothing but four separate, independent
projects, each subject to a separate NEPA analysis. Plaintiffs' entire lawsuit,
in contrast, presupposes that the several phases of the Project should be
aggregated and that an EIS should issue for the Project as a whole.
The characterization of
the Project is critical to this court's inquiry because the Government's contention
that Plaintiffs' suit for an EIS is moot with respect to Phases I and II and
unripe with respect to Phases III and IV makes sense only if the four phases
are properly treated as separate actions under NEPA. If, as Plaintiffs contend, they are merely components of one
"major federal action," Plaintiffs' suit to compel an EIS for that
action is neither moot nor unripe. It
would not be moot since so much of the Project remains to be done, and it
would not be unripe since the Project has already been partially implemented.
[FN5]
FN5. See discussion of the "proposal" requirement
infra at Section V.C.1.
The court finds that there is
insufficient evidence in the record to support a finding, at summary judgment,
that the Project is and always was a single, integrated, action with a solitary
purpose: the construction of
a 500 megawatt geothermal plant in Puna.
It is difficult to glean from the evidence presented just how clearly
and specifically the latter phases were defined at the time Phase I was proposed
and implemented in 1978. Accordingly,
there remain issues of fact as to whether the Project was and is, in actuality,
a single project with a single goal, or whether it began as mere background
research projects that did not ripen into a proposal for a full‑scale
geothermal energy plant until sometime later. This issue cannot, therefore, be resolved
by summary judgment.
Even accepting the Government's
contention that the four separate phases of the Project are distinct actions,
however, the court nonetheless finds that the Government *1457 is not entitled to summary judgment. The reasoning is set forth below.
A. The Four Phases As "Connected
Actions"
Even if the four phases of the
Project are considered separate actions triggering separate NEPA obligations,
those four actions (or phases) are sufficiently "connected" to require
that they all be evaluated in a single EIS.
The regulation that governs
the scope of EISs specifically provides for the consideration of:
(1) Connected actions, which means that they are closely
related and therefore should be discussed in the same impact statement.
Actions are connected if they:
(i) Automatically trigger other actions which may require
environmental impact statements.
(ii) Cannot or will not proceed unless other actions
are taken previously or simultaneously.
(iii) Are interdependent parts of a larger action and
depend on the larger action for their justification.
40 CFR § 1508.25(a).
Although the three subsections
are connected by neither "and" nor "or," it appears that
they should be read in the disjunctive rather than the conjunctive.
They are separated by periods, suggesting that each or any of the three
criteria should be sufficient, standing alone, to make the actions "connected." The case law interpretations of the regulation
have been consistent with this, having treated the separate subsections as
sufficient conditions, not necessary conditions. Hudson River Sloop Clearwater v. Dept.
of Navy, 836 F.2d 760, 763 (2d Cir.1988) (noting that "[o]nly subdivisions
(ii) and (iii) are at issue here," and then proceeding to analyze the
applicability of those subdivisions);
Town of Huntington v. Marsh, 859 F.2d 1134, 1142 (2d Cir.1988) (finding
the actions to be connected based solely on the satisfaction of subdivision
(iii)) (citing Save the Yaak Committee v. Block, 840 F.2d 714, 719 (9th Cir.1988)).
In this case, subsection
(i) clearly does not apply, subsection (ii)'s applicability is arguable, and
subsection (iii) appears to contemplate these facts precisely.
The latter two provisions will be discussed in turn.
1. Connected Actions Under Subsection (ii)
Actions are connected if they:
....
(ii) Cannot or will not proceed unless other actions
are taken previously or simultaneously.
40 CFR § 1508.25(a)(1).
Under subsection (ii),
it seems clear that Phase IV could never proceed unless Phases I‑III
were undertaken previously. Thus,
subsection (ii) arguably applies. The
Second Circuit has suggested, however, that the proper inquiry under (ii)
is not whether the more remote action can proceed absent the more immediate
action, but rather whether the more immediate action can proceed absent the
remote action. [FN6]
FN6. In this case, the immediate action is Phase III, the
action currently being proposed. The
more remote action is Phase IV. It is a different question to ask whether implementation of
Phase III is a necessary precondition for Phase IV than to ask whether implementation
of Phase IV is a necessary precondition for Phase III.
In Hudson River Sloop Clearwater
v. Dept. of Navy, 836 F.2d 760 (2d Cir.1988), conservation groups sued to
stop development of a Navy battleship homeport until the Navy filed an EIS
that also considered the accompanying proposal for the construction of housing
to serve the homeport. The court
observed:
With respect to subdivision (ii), the district court
concluded that the actions in this case are connected because the "construction
of the family housing will not proceed unless the operational aspects of the
homeport are built." We deem the issue presented, however, to be whether the converse
is true. In other words, will
the operational aspects of the homeport proceed without the construction of
family housing?
*1458 836 F.2d at 763. Concluding that the homeport would proceed whether or not the
housing project could be approved, the court ruled that, under subsection
(ii), the two actions were not connected. [FN7]
FN7. Hudson River Sloop cites Thomas v. Peterson, 753 F.2d
754, 758‑ 59 (9th Cir.1985) as an application of subsection (ii), observing
that it found connectedness where both actions are necessary preconditions
to the other. This court believes
Thomas is better characterized as an application of subsection (iii), discussed
infra.
Following the Second Circuit,
the issue is not whether Phase IV could go forward without Phases I‑III,
but rather whether the earlier Phases could go forward without Phase IV ever
being implemented. When characterized
this way, it seems clear that the answer is yes. Indeed, Phases I and II have already been
completed without any guarantee that Phase IV will ultimately be implemented.
Moreover, the actual language of subsection (ii) suggests that it has
no applicability when the more remote action follows the more immediate action:
Actions are connected if they:
....
(ii) Cannot or will not proceed unless other actions
are taken previously or simultaneously.
40 CFR § 1508.25(a)(1)
(emphasis added). Under this
characterization, the various phases would not be "connected actions"
under subsection (ii).
It is clear, however,
that the two major components of the Project, the cable construction and the
geothermal power plant construction, are necessary to each other. The 1988 Act stated:
(7) The fundamental interrelationship between the development
of geothermal resources and a cable system and the magnitude of the cost to
undertake each of these developments clearly indicate that neither will be
undertaken without the firm assurance that the other also will be undertaken
in a synchronized and coordinated manner to enable both developments in substance
to be completed concurrently....
H.R.S. § 196D‑2
(emphasis added). In a sense,
therefore, the work related to either of those components "will not proceed"
unless there is development of the other component. This argument, somewhat strained under
the language of subsection (ii), is more squarely advanced as an application
of subsection (iii), infra.
2. Connected Actions Under Subsection (iii)
Actions are connected if they:
....
(iii) Are interdependent parts of a larger action and
depend on the larger action for their justification.
40 CFR § 1508.25(a)(1).
This provision describes
the facts before the court accurately.
Phases I‑III appear to have been conceived for the sole purpose
of bringing about Phase IV, and depend on Phase IV and each other for their
justification.
Although the Ninth Circuit
has never explicitly relied on subsection (iii) in finding actions to be connected
for NEPA purposes, it has repeatedly applied a virtually identical standard.
It has, for example, specifically defined the interdependence that
must exist between the various phases of a larger project if they are to be
deemed connected:
The dependency is such that it would be irrational,
or at least unwise, to undertake the first phase if subsequent phases were
not also undertaken.
Save the Yaak Committee
v. Block, 840 F.2d 714, 719‑20 (9th Cir.1988) (quoting Trout Unlimited
v. Morton, 509 F.2d 1276, 1285 (9th Cir.1974)). The standard has been alternatively stated (as applied to a
highway project) as follows:
[T]he environmental impacts of a single highway segment
may be evaluated separately from those of the rest of the highway only if
the segment has "independent utility."
Thomas v. Peterson, 753
F.2d 754, 759 (9th Cir.1985) (summarizing the holding of Daly v. Volpe, 514
F.2d 1106, 1110 (9th Cir.1975)); see
also Fritiofson v. Alexander, 772 F.2d 1225, 1242 (5th Cir.1985) ( "
'Connected *1459 actions' are defined
in a manner consistent with the criteria recognized in the independent‑utility
cases."). [FN8]
FN8. The Second Circuit has affirmatively acknowledged that
this "independent utility" test is merely an application of subsection
(iii). See e.g. Town of Huntington v. Marsh, 859 F.2d 1134, 1141‑42
(2d Cir.1988) ("The proper test to determine relatedness under 40 CFR
§ 1508.25(a)(1)(iii) is whether the project has independent utility.");
Hudson River Sloop Clearwater v. Dept. of Navy, 836 F.2d 760, 764 (2d Cir.1988)
("[S]ubdivision (iii) has been determined to mirror a line of cases which
hold that the proper test for interdependence is one of independent utility.").
The Ninth Circuit elaborated
on the application of this "independent utility" test in Thomas
v. Peterson, 753 F.2d at 759‑60:
In the light of Trout Unlimited, the phrase "independent
utility" means utility such that the agency might reasonably consider
constructing only the segment in question.
In Thomas, there were
two proposals: one for timber
harvesting and sales, and another for construction of a road into the area
to be harvested. The Ninth Circuit
ruled that because the harvesting could not be done without construction of
the road, and because the road did not have any significant utility other
than to facilitate the harvesting, NEPA required a single EIS covering both
the road and the timber sales. Id.; see also Morgan v. Walter, 728 F.Supp.
1483, 1493 (D.Idaho 1989) (David A. Ezra, District Judge) (Proposed diversion
of river and proposed fish propagation facility are "connected actions"
because "the fish propagation facility could not exist absent a diversion"
and because the diversion was proposed for the purpose of facilitating fish
propagation.).
On the facts before this
court, Phases I‑III do not possess any real independent utility.
If Phase IV were not a possibility, it would clearly be "irrational,
or at least unwise" to proceed with Phases I‑III.
Trout Unlimited, 509 F.2d at 1285.
The Government could not "reasonably consider" going ahead
with the deep water cable research and construction if there were no geothermal
energy development to utilize the cable.
Thomas, 753 F.2d at 760. Neither
would the geothermal energy be developed if there were no cable project to
convey the power generated. See
the 1988 Act, H.R.S. § 196D‑2. The facts of Thomas‑‑timber
project and access road‑‑are analogous. Most significantly, there is no "independent utility"
to the drilling of 25 commercial size wells to "verify" a geothermal
resource (Phase III); that action
is "irrational" absent imminent construction of a geothermal power
plant (Phase IV).
Accordingly, even if the
Project is properly characterized as four separate phases, the court would
hold that those four phases are "connected actions" under NEPA regulations,
and should be the subject of a single EIS. [FN9]
FN9. Given the mootness of Phases I and II, see infra Section
V.B., this finding of connectedness is effective only as to the remaining
actions, Phases III and IV.
B. Mootness
Even though the actions are
connected, Phases I and II have already been completed. Any attempt to have those actions considered
in a comprehensive EIS is, therefore, moot. [FN10]
FN10. Phase I was the subject of an environmental assessment
(EA) under NEPA, the adequacy of which was challenged in Puna Speaks v. Edwards,
554 F.Supp. 117 (D.Haw.1982) (finding the EA to comply with the statute, and
refusing to compel an EIS). In
order to compel an EIS considering all four phases, Plaintiffs should have
challenged the adequacy of the EA for Phase I, arguing that the remaining
three phases were "connected actions." Plaintiffs in this
case were not parties to the Puna Speaks action, and it does not appear from
the opinion that any "connected action" argument was raised at that
time.
As discussed above in Section
IV, NEPA's function is to assure that adequate information is provided at
the decision‑making stage on a proposed action.
[T]he basic function of an EIS is to serve as a forward‑looking
instrument to assist in evaluating "proposals" for major federal
action....
*1460 National Wildlife Fed. v. Appalachian Reg. Commission,
677 F.2d 883, 889 (D.C.Cir.1981) (quoting Aertsen v. Landrieu, 637 F.2d 12,
19 (1st Cir.1980) (citing Kleppe v. Sierra Club, 427 U.S. 390, 410 n. 20,
96 S.Ct. 2718, 2730 n. 20, 49 L.Ed.2d 576 (1975))) (emphasis supplied by the
Appalachian court).
Where the decision has
already been made and carried out, and the action taken cannot be undone,
there is absolutely no function or role for an EIS. Any suit to compel an EIS at that point is, perforce, moot. Sierra Club v. Penfold, 857 F.2d 1307,
1317‑18 (9th Cir.1988) (suit challenging mining operations; the suit for an EIS is moot because "no
adequate remedy exists.... [A]
completed mining project cannot be moved," distinguishing Columbia Basin
Land Protection Assoc. v. Schlesinger, 643 F.2d 585, 591 n. 1 (9th Cir.1981)
(suit over placement of power lines is not moot since the court could order
that the power line be moved)); see also Friends of the Earth, Inc. v. Bergland, 576 F.2d 1377,
1378‑79 (9th Cir.1978) (claim is moot because the challenged mining
project ended before the appeal was heard); Ogunquit Village Corp. v. Davis, 553 F.2d 243, 246‑47
(1st Cir.1977) (courts cannot provide post‑ completion relief under
NEPA).
Thus, whatever EIS might
ultimately be ordered if Plaintiffs are successful in this suit can be directed
only toward the remaining work to be done.
[W]hen a NEPA challenge is leveled against some subsequent
phase of a continuing federal action, the EIS obligation attaching at the
latter point is realistically qualified by the elements of the program already
in place. This limitation simply
confines NEPA's mandatory decisionmaking input to programs posing options
that may still freely be chosen.
Appalachian, 677 F.2d
at 890. The actions taken in
Phases I and II are complete and cannot be made the subject of any EIS; rather their effects should be incorporated
into the background "data base" for assessment of the phases still
at issue. See Coalition on Sensible
Transp., Inc. v. Dole, 826 F.2d 60, 70 (D.C.Cir.1987).
C. Ripeness
As to the remaining phases,
the Government contends that there is no proposal yet before it, and that
the suit to compel an EIS is therefore unripe. Coupled with this contention is the Government's promise that
the appropriate environmental assessment will be done for Phase III before
that project is undertaken. These
alternative, if somewhat inconsistent, arguments will be considered in turn.
1. The Proposal Requirement‑‑Triggering the NEPA
Duty
It is now well settled
that an EIS cannot be required unless and until a "proposal" is
made. Kleppe v. Sierra Club,
427 U.S. 390, 96 S.Ct. 2718, 49 L.Ed.2d 576 (1975). In Kleppe, the Department of Interior was involved in leasing
government property to be mined, and the Sierra Club sought to compel an EIS
for the entire region then being leased. The Court of Appeals found that the Department "contemplated"
a regionwide plan or program, even though its only activity had been the entering
of individual leases, and ordered that an EIS be prepared.
The Supreme Court reversed, saying that the statute does not require
an EIS until an agency makes a report or recommendation on a proposal.
Whether or not regionwide action was contemplated, there was no proposal
for such regionwide action, and the EIS could not be compelled. See also Aberdeen & Rockfish R. Co.
v. SCRAP, 422 U.S. 289, 320, 95 S.Ct. 2336, 2356, 45 L.Ed.2d 191 (1974) ("[T]he
time at which the agency must prepare the final [environmental impact] 'statement'
is the time at which it makes a recommendation or report on a proposal for
federal action.") (emphasis in original); B.R.S. Land Investors v. United States,
596 F.2d 353, 355 (9th Cir.1979) (utility applied for federal approval for
high‑tower power lines over federal land;
although there had been "preliminary discussions" on the
application, there was no federal action sufficient to trigger NEPA).
Despite its attempt to
establish a bright‑line test, the Kleppe decision does not dictate
*1461 a clear conclusion in this case.
One commentator has observed:
The Supreme Court's decision in Kleppe leaves many questions
unanswered. The Court stated that NEPA requires a "precise" decision
on whether an agency has "proposed" an action, but it did not define
"proposal." ....
Mandelker, NEPA Law &
Lit. § 8:13 (1990). Indeed this
fact pattern does not seem to fit within the parameters contemplated by Kleppe
or by any other reported decision.
In the more typical scenario,
a federal agency considers a private proposal, then issues a report or recommendation
on it before the proposed action is taken. Kleppe and its progeny clearly establish
that the EIS must be completed at the time such report or recommendation is
made. If Congressional action
is required, the proposal, the report or recommendation, and the EIS all go
to Congress for consideration.
In this case, however,
the proposal was submitted directly to Congress, and DOE did not issue a report
or recommendation on it. DOE's
failure to issue such a report or recommendation has already frustrated to
some degree NEPA's purposes in that Congress acted on the proposal without
being advised or informed of its potential environmental impact. The Government now argues that it may
use the appropriated funds to contract for the work comprising Phase III before
it can be compelled to look at the environmental consequences of that action.
This approach appears
to be in conflict with NEPA's clear intent, as interpreted by the accompanying
regulations:
The [environmental impact] statement shall be prepared
early enough so that it can serve practically as an important contribution
to the decisionmaking process and will not be used to rationalize or justify
decisions already made.
40 CFR § 1502.5. The Ninth Circuit has joined in this refrain,
stressing that "[t]he purpose of an EIS is to apprise decisionmakers
of the disruptive environmental effects that may flow from their decisions
at a time when they 'retain[ ] a maximum range of options.' " Conner v. Burford, 848 F.2d 1441, 1446
(9th Cir.1988) (quoting Sierra Club v. Peterson, 717 F.2d 1409, 1414 (D.C.Cir.1983))
(emphasis added), cert. denied sub nom. Sun Exploration and Production Co.
v. Lujan, 489 U.S. 1012, 109 S.Ct. 1121, 103 L.Ed.2d 184 (1989). In any case, the statement "must
be prepared before any irreversible and irretrievable commitment of resources."
Conner v. Burford, 848 F.2d at 1446.
The Ninth Circuit has further warned that "delay in preparing
an EIS may make all parties less flexible.
After major investment of both time and money, it is likely that more
environmental harm will be tolerated."
Environmental Defense Fund v. Andrus, 596 F.2d 848, 853 (9th Cir.1979).
The decision to commit
$5 million of federal funds to Phase III of the Project has already been made. It may be, therefore, that some kind of
NEPA compliance‑‑an environmental assessment or EIS‑‑may
in fact already be due. Nonetheless, the U.S. Supreme Court requires a "proposal."
Although Kleppe fails
to define "proposal", the regulations provide some assistance in
this regard:
"Proposal" exists at that stage in the development
of an action when an agency subject to the Act has a goal and is actively
preparing to make a decision on one or more alternative means of accomplishing
that goal and the effects can be meaningfully evaluated.... A proposal may exist in fact as well as
by agency declaration that one exists.
40 CFR § 1508.23. This definition is plainly geared toward
a more general, functional interpretation of the term, not the literal interpretation
urged by the Government.
In this case, the agency,
DOE, clearly "has a goal" of implementing Phase III, and it is apparent
that its ultimate goal is to see Phase IV through. There is evidence that the Department
of Interior shares this goal. If
DOE is, as it suggests, soliciting or drawing up contracts to perform the
work, it "is actively preparing to make a decision on one or more means
of accomplishing that goal." The
fact that *1462 DOE has not set forth
any written "proposal" is immaterial because "a proposal may
exist in fact as well as by agency declaration." Id.
The fact that Congress
has already appropriated $5 million for Phase III clearly establishes that
some kind of proposal has been made.
In National Wildlife Fed. v. Coston, 773 F.2d 1513 (9th Cir.1985),
the Ninth Circuit addressed the significance of appropriations in triggering
NEPA obligations. The court held that while the appropriations themselves
are not major federal action, Id. at 1518, they are the "fund[ing of]
actions already proposed." Id. at 1518 (quoting Andrus v. Sierra Club,
442 U.S. 347, 362, 99 S.Ct. 2335, 2343, 60 L.Ed.2d 943 (1979)) (emphasis added). Because NEPA already applies to, and an
EIS duty has already arisen for, the proposed action for which the appropriation
is made, any EIS requirement for the appropriation itself would be redundant.
Id.
Based on this analysis,
the $5 million appropriation was made to fund the "already proposed" federal action herein characterized
as Phase III. Because a proposal
must be deemed to have been made to secure the appropriation, the suit to
compel an EIS appears to be, under this approach, clearly ripe. Moreover, because the money has been appropriated,
the Government is clearly in the decision‑making mode‑‑that
in which an EIS is required‑‑deciding precisely how the money
will be disbursed and/or how the action will be carried out. There is no risk that the EIS will ultimately
prove unnecessary. See Kleppe,
427 U.S. at 406, 96 S.Ct. at 2728 (because many "contemplated" projects
do not ever ripen into "proposals," EISs for such contemplated projects
would be unnecessary wastes of resources).
This is a case in which a proposal "exist[s] in fact," whether
or not it has ever been formally advanced as such.
40 CFR § 1508.23.
Further, there are additional
grounds for finding a "proposal" here. Congress was not acting in a vacuum.
It appropriated the money for Phase III in response to an extensive
and detailed "Proposal to Establish the Hawaii Geothermal Resource Verification
and Characterization Program," prepared by the Hawaii Department of Business
and Economic Development, and submitted to Congress by the State of Hawaii
in March 1990 (the "Hawaii Proposal").
In light of DOE's significant role in the greater Project, this is
clearly a "proposal" sufficient to trigger NEPA obligations.
The Government cannot
argue that this was simply a private proposal which it may yet dismiss without
any need for an EIS. See Daingerfield
Island Protective Society, Inc. v. Andrus, 458 F.Supp. 961, 963 (D.D.C.1978)
(rejecting plaintiff's contention that "the Government, prior to accepting
or rejecting a private proposal submitted to it, must have prepared an EIS.").
Under the "state/federal partnership" characterization the
Project has received, the state's proposal might even be deemed DOE's proposal
as well. And even if the Hawaii
Proposal could be properly termed a "private proposal," the proposal
has been accepted by act of Congress, and has now been served into DOE's court
with that formal federal imprimatur.
Now that the proposal
is before DOE, NEPA requires that work begin on the prescribed environmental
assessments. Under the regulations,
such work must begin immediately:
An agency shall commence preparation of an environmental
impact statement as close as possible to the time the agency is developing
or is presentedwith a proposal.
40 CFR § 1502.5
To rule that a proposal
on which Congress has already acted is not ripe for NEPA purposes, i.e., does
not trigger NEPA obligations, would elevate form over substance. A proposal exists since "an agency
subject to the Act has a goal and is actively preparing to make a decision
on one or more alternative means of accomplishing that goal." 40 CFR § 1508.23. Moreover that proposal has been given
Congressional blessing. The time
appears to be ripe for preparation of an EIS.
*1463 A separate question remains, however, of whether the
time is ripe for an action to compel an EIS.
2. Ripeness of an Action to Compel NEPA Compliance
At the hearing, the Government
stressed that federal agencies are entitled to a presumption of regularity,
and promised that DOE would take steps to comply with NEPA. Government counsel cited the Declaration
of John E. Mock, Director of DOE's Geothermal Division:
DOE is currently preparing a statement of work for a
contract to implement the congressional language cited above. As yet, DOE has not contracted with the
State for the verification or characterization work to be performed by the
State. Prior to any verification
or characterization work being undertaken with these funds, DOE will prepare
or have prepared for its evaluation under NEPA the appropriate environmental
analysis.
Mock Declaration, õ 7.
There is a certain inconsistency
in the Government's position, however. In its briefs, and as discussed supra, the Government has argued
that no proposal has been submitted to DOE, and that no duty to perform an
Environmental Assessment accrues until there is both a proposal submitted
and a report or recommendation from the agency on that proposal. Government counsel promised that if and
when some "triggering" event occurs (e.g., a permit application),
the applicable agency will not take action (approve the permit) without first
jumping through the necessary NEPA hoops.
Aside from the issue of
when NEPA obligations are first triggered is the issue of when an agency's
compliance (or noncompliance) with NEPA may be challenged and/or enjoined. By arguing that DOE should be given a
chance to comply with NEPA and that the agency is already "in the process"
of such review, the Government implicitly admits that NEPA obligations have
been triggered. The Government's
argument then focuses on the contention that its compliance cannot be challenged
or enjoined until the time has come for that compliance to be complete.
The Government's position is apparently that no injunction can be sought
or issued until the money is transferred or contracts are entered. Until that time, the Government asserts
that it is entitled to a "presumption of regularity."
Plaintiffs contend, on
the other hand, that there is nothing left for DOE to do in this situation
except hand the money over to Hawaii's DBED, and even this transfer is not
in DOE's discretion. They argue
that because no further federal approvals are necessary before the $5 million
is used to commence work on Phase III, there is no date certain by which NEPA
compliance must be complete and at which review of such compliance would be
any riper than it already is.
a. The Presumption of Regularity
The best articulation
of the relevant law on an agency's "presumption of regularity" comes
from Conner v. Burford, 848 F.2d 1441 (9th Cir.1988). Conner was a challenge
to the sale of oil/gas leases in vast areas of national forest. The suit was based on the government's
failure to prepare an EIS as required by NEPA before selling the leases. The court found that the leases contained
"no surface occupancy" ("NSO") stipulations prohibiting
any surface‑disturbing activity, and therefore did not have significant
environmental consequences. It
concluded that an EIS for such leases could be required only upon the
[m]odification or removal of an NSO stipulation ...,
which ... would constitute an irretrievable commitment of resources requiring
the preparation of an EIS.
Conner, 848 F.2d at 1447‑48.
The court refused to anticipate such alteration of NSO stipulations:
We cannot assume that government agencies will not comply
with their NEPA obligations in later stages of development. Cf. Citizens to Preserve Overton Park
v. Volpe, 401 U.S. 402, 415, [91 S.Ct. 814, 823, 28 L.Ed.2d 136] (1971) (agency
action entitled to presumption of regularity).
*1464 Id. at 1448. [FN11]
FN11. The Overton Park case was a challenge to the Secretary
of Transportation's approval of a highway through a state park. In finding that the plaintiffs had submitted
insufficient evidence that the Secretary had exceeded his authority in giving
such approval, the U.S. Supreme Court observed:
Certainly, the Secretary's decision is entitled to a presumption of
regularity. But that presumption
is not to shield his action from a thorough, probing, in‑depth review.
401 U.S. at 415, 91 S.Ct. at 823 (citations omitted). The Court also noted that the Secretary's
decision could be overturned if " 'arbitrary, capricious, an abuse of
discretion, or otherwise not in accordance with law.' " Id. at 416, 91 S.Ct. at 823 (quoting 5
U.S.C. § 706(2)(A)).
Conner relied on Sierra Club
v. FERC, 754 F.2d 1506 (9th Cir.1985), in which a "preliminary permit"
for a hydroelectric project had been issued without conducting an EIS.
The court in Sierra Club ruled that because the preliminary permit
did not authorize any activity on federal land, but functioned simply to maintain
the applicant's priority of application for a license, no EIS could be required.
Id. at 1509. The court
observed that "[p]etitioners can only enter federal land and conduct
ground‑breaking activities after obtaining Forest Service and BLM special
use permits." Id. Because
the court found that action affecting the environment could not take place
until the permits were issued, the requirements of NEPA could be fully met
by conducting the EIS at that later stage.
b. Where the Agency Denies Any Duty
In this case, however, the Government
has argued that there is/was no proposal before DOE, and there is/was, therefore,
nothing for DOE to act on. As discussed above, Government counsel suggested
that NEPA obligations would be triggered if a permit were applied for, but
refused to speculate as to what, if any, permits might be necessary before
work on Phase III begins.
Where the agency is arguing
that it has no obligation to do anything under NEPA, the court cannot presume
that the agency is, at the same time, carrying out the environmental assessments
that NEPA requires. Any such
"presumption of regularity" is waived or at least vitiated by the
Government's contention that it has no NEPA duty whatsoever.
The inquiry does not end here,
however, because the Government does not rely solely on its denial of duty
argument.
c. The Point at Which NEPA Compliance May Be Reviewed, Challenged,
or Compelled
The Government has also argued
that "DOE is currently preparing a statement of work for a contract to
implement the congressional language" and that "the appropriate
environmental analysis" will be done before any work on Phase III is
undertaken with federal funds. Mock
Declaration, õ 7. As noted earlier,
this argument essentially concedes that NEPA obligations have been triggered,
and the issue shifts to the question of when the obligation which presently
exists can be compelled.
The "presumption of regularity"
suggests that this court should assume that DOE will fully comply with its
NEPA obligations, and should not interfere until the time has come for such
compliance to be complete. At
that point, the court can evaluate the adequacy of the compliance, and compel
any actions required by law that have been overlooked. The Government suggests that such a time
will not be reached in this case until contracts are entered for the performance
of the work contemplated by Phase III.
Even if DOE has a role in contracting
for the work in Phase III, however, this suit will not necessarily be unripe.
The Ninth Circuit has held that when the agency is committed to implementing
a project, a suit to compel NEPA compliance need not be delayed until the
contracting stage. In Environmental Defense Fund v. Andrus,
596 F.2d 848 (9th Cir.1979), the Department of Interior announced a program
for marketing reservoir water for industrial uses. The court ruled that the Plaintiffs need
not await the entering of actual contracts:
Here the Secretary of Interior has no intention of abandoning
plans for marketing industrial water and is prepared *1465 to execute water option contracts. NEPA does not permit delay in assessing
the environmental impact of the marketing plan.
Id. at 852. [FN12] Here, given the $5 million appropriation
already made for Phase III, as well as the previous undertaking and completion
of Phases I and II, the evidence may show that the Secretary of Energy similarly
"has no intention of abandoning plans" to implement that Phase.
In such a scenario, under Andrus, NEPA will not permit further delay,
regardless of whether DOE will later be entering into contracts.
See also Lathan v. Volve, 455 F.2d 1111, 1121 (9th Cir.1971) ("If
defendants' contention were accepted‑‑that no environmental impact
statement is required until the final approval stage‑‑then it
could well be too late to adjust the formulated plans so as to minimize adverse
environmental effects.")
FN12. It is noteworthy that the Ninth Circuit also recognized
that each water option contract required a separate EIS. The court held that such "EIS[s]
must be prepared prior to execution of an option contract." Andrus, 596
F.2d at 852 (emphasis added).
There is some question, however,
as to the role DOE will play in contracting for the Phase III work.
The Congressional action does not authorize DOE to "contract"
for that work. It simply provides the $5 million to the
State DBED:
The Committee recommendation also includes $5,000,000
for the State of Hawaii through its [D]epartment of [B]usiness and [E]conomic
[D]evelopment to continue the Hawaii geothermal resource verification and
characterization projects to help reduce the State's dependency on fossil
fuels. The State of Hawaii has
assured the Committee that this cost‑shared assessment will be conducted
consistent with the State's outstanding effort to protect and preserve its
unique natural resources.
Conference Report 101‑889,
Oct. 16, 1990 to accompany HR 5019.
This language suggests, and Plaintiffs argue, that Congress did not
envision a contracting role for DOE.
Rather, it provided the money to DBED based on assurances from the
state about how the money would be used, apparently leaving the contracting
in the state's hands and discretion.
If this is the case, these
facts are distinguishable from Conner and Sierra Club, both of which anticipated a specific future event,
a future federal decision whether to permit the environment‑threatening
project to go forward. The action
already taken in this case, Congressional appropriation of $5 million for
the express purpose of implementing the "already proposed" Phase
III, may actually be sufficient for work to begin.
Neither party has identified any kind of further approval that will
be needed before the work on Phase III may commence. [FN13]
FN13. The Government has suggested that further permits might
be required, and has argued that it is at such a juncture that an EIS could
be compelled. But when Government
counsel was asked by this court what permits will be required or applied for,
he insisted, "I have no idea."
If there is no further federal
approval required, if there is no substantial and significant decision‑making
role left for DOE before committing itself to implementing Phase III, the
suit to compel NEPA compliance is as ripe as it will ever be. Conner and Sierra Club do not control
to defeat ripeness unless there is a future point, clearly identified, at
which NEPA compliance must be complete and can be reviewed, challenged or
compelled. Andrus controls to
establish ripeness if that future point is the mere implementation of a project
or program already embraced and adopted.
This gives rise to a material
issue of fact. The court needs
more information on DOE's level of commitment to the implementation of Phase
III, as well as the precise role that DOE expects to play, will play, and/or
must play in the disbursement of the $5 million. If, as the conference report language suggests, DOE has little
or no discretion, but must transfer the money directly to DBED, then the time
is ripe to consider the adequacy of DOE's NEPA compliance. If, on the other hand, *1466 the disbursement of the funds is subject to DOE contracting,
and DOE will have to prepare proposed contracts on which it will make recommendations,
exercising a discretionary, decision‑making role, an action to compel
an EIS may be ripe only at that later time.
The presence of these material
issues of fact preclude summary judgment as requested by the Government at
this stage. Resolution of the
issue presented will require further factual findings at trial.
VI. Major Federal Action‑‑Plaintiffs'
Motion for Partial Summary Judgment
The issue is raised in Plaintiffs'
Cross‑Motion whether the participation of the Government in the Project,
as outlined above, constitutes "major federal action" as a matter
of law. Plaintiffs have moved
for summary judgment on this issue, reserving the remaining two issues for
trial. [FN14]
FN14. The issues which would remain for trial are (1) whether
such action "significantly affect[s] the quality of the human environment,"
and (2) what is the appropriate remedy.
A. The Regulations
The applicable regulations
define "major federal action" to include, inter alia, "new
and continuous activities, including projects or programs entirely or partly
financed, assisted, conducted, regulated, or approved by federal agencies...."
40 CFR § 1508.18(a).
The Government has attempted
to de‑emphasize the participation of the various defendant agencies
in the Project (stressing that the more significant involvement of such agencies
will not come until Phase IV), and both parties have argued the significance,
or insignificance, of the Interagency Group. The Government relies on Almond Hill School v. U.S. Dept. of
Agriculture, 768 F.2d 1030 (9th Cir.1985) to argue that such limited participation
of federal employees has not been sufficient to turn this local project into
major federal action. In Almond
Hill, California undertook a beetle eradication project, and put three federal
government officials on the project's eight‑member board of advisors.
Although their salaries were paid with federal funds, these officials
did not have a decision‑making role.
The Ninth Circuit found that the payment of salaries was not a significant
enough commitment of federal funds to make the eradication project a "major
federal action." 768 F.2d at 1039.
The Government argues that the
tangential involvement of salaried federal officials in this case is similarly
insufficient to make the Project a federal action. The Government is straining at a gnat
but swallowing a camel. [FN15] In addressing the issue of the role of federal
officials in the Project, the Government overlooks the near $40 million in
federal funds directly contributed to the Project. Almond Hill is easily distinguished because in that case, as
the court emphasized, "no federal funds [were] sought by the state or
spent on the state's beetle eradication project." Id.
FN15. See Matthew 23:23‑24 (KJV).
There is no dispute as to the
degree of the Government's financial participation in the Project. The use of federal funds, especially in
such amounts and to such a degree (over 80% of total funding) is enough standing
alone to render the Project "major federal action." See, e.g., State of Alaska v. Andrus,
591 F.2d 537, 540 (9th Cir.1979) ("Most courts agree that significant
federal funding turns what would otherwise be a local project into a major
federal action."); Homeowners
Emergency Life Prot. Committee v. Lynn, 541 F.2d 814 (9th Cir.1976) ("Inasmuch
as the grant of federal funds unquestionably moves the activity in issue to
the point of a federal‑city partnership, the project is now a major
federal action.").
No matter whether the Project
is considered as a single multi‑faceted program or segmented into four
separate and independent projects, there can be little question that it is
major federal activity. Indeed,
each of the first three phases independently has received sufficient federal
financial funding to qualify as a major federal action: Phase I received $10.7 million; *1467
Phase II received $24 million; and Phase III has already received $5
million with two more installments of $5 million each likely to come. Although it is not apparent from the record
how much, if any, federal money will be utilized in Phase IV, it is clear
from the list compiled by the Interagency Group that the federal government
will be heavily involved in a permitting role at that stage. [FN16]
Therefore, even if federal financing at that stage is not significant,
Phase IV will nonetheless qualify as major federal action because it is a
"project[ ] [or] program[ ] entirely or partly ... regulated, or approved
by federal agencies." 40 CFR § 1508.18(a).
FN16. In fact, the Government defends Plaintiffs' Cross‑Motion
by arguing that most of the defendant federal agencies are not yet involved
and will not become involved until the Project reaches the permitting stage
in Phase IV. In so arguing, the
Government acknowledges the important role numerous federal agencies will
have in Phase IV.
The enormous commitment of federal
resources to the Project easily establishes it as major federal action.
These facts are not in dispute, and no facts are alleged which, if
proven, could make it otherwise. Further,
in addition to the substantial financial commitment to this Project, the court
has outlined above the Government's additional substantial involvement and
participation at every stage of the Project's history.
See Section II.C. supra. Plaintiffs
are entitled to partial summary judgment declaring the Government's involvement
in the Project to be major federal action.
VII. Conclusion
Whereas material issues of fact
remain regarding (1) the Government's, specifically DOE's, commitment to implementation
of Phase III, and (2) DOE's role with respect to the $5 million appropriation,
the Government's motion for summary judgment is DENIED. As the Government's involvement in the
Project constitutes major federal action for purposes of NEPA, Plaintiffs'
motion for partial summary judgment is GRANTED.