| Date |
Milestone |
Status |
| 8/2/2002 |
Luminis software installed and
configured
|
Done
|
| 10/17/2002 |
Portal Implementation team formed
|
Done
|
| 1/6/2003 |
Email system integrated
with Luminis
|
Done
|
2/7/2003
|
Portal Authentication using LDAP completed
|
Done
|
| 4/25/2003 |
Banner extract programs modified to accomodate VPD db |
Done
|
| 5/2/2003 |
Production WebCT server installed and configured. |
Done |
| 5/16/2003 |
Mercury Message Broker installed
and configured.
MMB training completed. |
Done |
| 6/6/2003 |
Internal usability and
general portal testing completed. |
Done |
| 6/17/2003 |
Banner integration components
installed, events turned on
and tested. (Verify events in Banner are sending data to
Luminis and WebCT) |
Done |
| 6/24/2003 |
Functional portal testing
completed |
Done |
| 7/21/2003 |
All channels implemented for 8/18
go live date
|
Done |
| 7/25/2003 |
LDAPs/NIS/Portal Synching code completed
|
Done |
| 9/9/2003 |
Communication to users of
9/22 rollout completed
|
Done |
| 9/10/2003 |
Test data load completed
|
Done |
| 9/14/2003 |
Look and Feel production ready on production and test servers
|
Done |
| 9/14/2003 |
Unison1 to Unison2 conversion completed
|
Done |
| 9/16/2003 |
'Essential' User documentation completed
|
Done |
| 9/22/2003 |
Banner Metadirectory Synching
(triggers and polling)
|
Done |
| 9/22/2003 |
Production data load completed
|
Done |
| 9/22/2003 |
Portal for all UH students, faculty and staff goes live
|
Completed! |
| 5/20/2004 |
New Portal version 3.1 released
|
Done |