Keller Data Center: Scheduled Keller Generator Maintenance Notification

SUMMARY: Keller Data Center: Scheduled Keller Generator Maintenance Notification
POSTED ON: 12/18/2012
REPORTER: Janice A Kawachi (kawachi)
START TIME: Dec 21 12:00 PM
END TIME: Dec 21 12:01 PM
DESCRIPTION: ITS will be performing generator maintenance at our Keller Hall Data Center. This activity should not be service impacting. During this period, we will transfer power from the Keller generator back to HECO power.

At any time during the activity, you can call the IT Operations Center at 956-6168 for status information or additional details.
UPDATE:12/21/2012 04:00 PM: Maintenance has been completed.