From: UH Office of Capital Improvements 
Subject: Additional Notice to Ongoing Project - IT Center
Date: April 19, 2013 4:52:09 PM HST
To: announce@HAWAII.EDU

NOTICE OF CONSTRUCTION

PROJECT:
INFORMATION TECHNOLOGY CENTER
UH 06-546

CONTRACTOR:
dck pacific construction, LLC

SCOPE OF WORK:
This notice is for a change in work hours of the previously issued notice.  The Contractor will be
back filling at the 8" water line connection to the 12" water main on Correa Road fronting the IT
Center site, installing a gate valve riser, and applying a temporary asphalt patch on the road.

DURATION AND HOURS OF WORK:
Saturday, April 20, 2013, 12:00 Noon to 7:00 pm; Monday, April 22, 2013, through Wednesday, April
24, 2013, 7:00 am - 3:30 pm

ADVISORY:
During this activity, the contractor will be reducing the traffic on Correa Road to one lane.
Flaggers will be provided. Please obey traffic flaggers.


The project team appreciates your patience, understanding, and cooperation to help maintain a safe
environment during construction. Thank you.

CONSTRUCTION MANAGEMENT CONTACT:
If you have any questions or concerns regarding this notice, call Kurt Kunimune, Bowers + Kubota
Consulting, Construction Manager, at 479-0767, or email kkunimune@bowersandkubota.com . For after
hours emergencies, contact Campus Security at 956-6911.

Mahalo.


-- 

This message was sent on behalf of UH Office of Capital Improvements. 
Please do not reply to this message.
It was sent from an address that cannot accept incoming email.

Announcement ID number: 1366426263-10324
Announcement distribution:
     - Faculty, staff, and all students at the UH Manoa campus(es)
     - Faculty and staff at the UH System Administrative Offices