Phytoremediation of EDB


"Long term, cost effective agriculture-based chemical cleanup solution"

Project Objectives
Demonstrate phytoremediation of ethylene dibromide (EDB). A phytoremediation system has been designed to remove and treat potential contamination sources and to mitigate migration of the contamination to the basal aquifer.

Status
On-going.

Activities
March 1998: Start bench-scale Treatability Investigation
July 1998: Detailed analysis and design
July 1998: Prepare Technical Memorandum for demonstration
Sept. 1998: Finalize Treatability Investigation report
Dec. 1998: Interim progress report
April 1999: First quarterly round of water sampling at Kunia; Irrigation of pilot-scale treatment units; Air monitoring over bench-scale treatment units begins; Finalize feasibility study technical memorandum

Benefits
Benefits both civilian and military communities through the development of an environmentally preferred alternative to conventional remediation. Cost effective, alternative technology for the remediation of contaminated perched ground water & soils at the site. Current project operations cost savings estimates are approximately $625,000 (through cost avoidance). Phytoremediation is estimated to be 571 times less costly than thermal desorption, and 1.5 times less costly than carbon adsorption. This technology is transferable to a wide range of civilian and military sites.