Aloha Kauʻiokahaloa Nui residents and Neighbors,
University Housing received the following update regarding the Woodlawn Drive Bridge Stream Project:
UPDATE – Mānoa Stream Improvements at Woodlawn Drive Bridge, DLNR Job No. J38CO56A
CONTRACTOR:
Frank Coluccio Construction Company
SCOPE OF WORK:
Continuation of Phase 1 Construction – Upstream, underneath and downstream areas of the existing Woodlawn Drive Bridge.
8/20/18 to 8/23/18, the Contractor will be removing stream BMP’s, soil piles and securing their construction yard, in anticipation of Hurricane Lane.
Tentatively 8/27/18 to 8/31/18, the Contractor will re-establish Best Management Practices (BMPs). BMPs are practices used to reduce runoff around the project site and within the stream. Setup ecology blocks and temporary bypass pipe within the stream.
Tentatively 8/27/18 to 9/14/18, the Contractor will begin stream dredge work.
Tentatively 9/17/18 to 9/28/18, the Contractor will begin the removal of stream bank trees and landscaping.
Large trucks and excavator(s) will be used around all areas of the Bridge (ʻEwa / Koko Head & Mauka / Makai).
DURATION OF PROJECT:
Phase 1: Schedule will be reassessed after storm and re-establishing BMP’s
Phase 2: Tentatively, Monday, October 1, 2018 – May 31, 2019
HOURS OF CONSTRUCTION: Monday – Friday, 8:00 am – 5:00 pm
ACCESSIBLE ROUTES: Accessible routes along the Woodlawn Drive Bridge and sidewalks will not be affected, except for the beginning and end of the workday when equipment is moved to continue work and stored overnights and weekends in the base yard.
ADVISORY: All persons in the vicinity of this construction project are advised to respect all construction barricades and all posted safety/detour signs. Your patience, cooperation and understanding are requested as the inconveniences inherent to construction (noise, dust, odors and debris) are generated by this project.
Organizers of upcoming UHM events or ad hoc projects in the vicinity of the construction project are encouraged to contact the Construction Manager to discuss coordination to avoid any conflicts.
PROJECT CONSTRUCTION MANAGEMENT CONTACT: Anyone with questions, concerns or comments regarding this Notice of Construction may call Joseph Hart, Project Construction Manager, at (808) 216-4918, or e-mail at joseph@hcahawaii.com.
PROJECT UPDATE INFORMATION: http://dlnreng.hawaii.gov/blog/2018/06/25/manoa-stream-improvements-at-woodlawn-drive-bridge/
We are committed to timely communication and will be providing regular updates via email as the project progresses.
Sincerely,
Andy Lachman
University Housing Manager